  • Project Goal
    Design a machine to fill, test and purge a diesel engine within 30 seconds in preparation for the next engine to be tested.
  • Project Result
    A high speed diesel engine testing system that integrates perfectly into the existing production line.
  • Project Location
    Huntsville, AL

Details

This cooling system and pumping station were designed as part of an exsisting production line to fill and purge an engine of coolant within 30 seconds in preparation for the next engine to be tested. It also required a complex set of instrumentation that provides results from the engine test. Custom pneumatic systems were also required in order to purge engine systems in the time allotted.

All these systems were packed, as always, in an easily shipped and maintained skid mounted system with a compact, intuitive, central control panel.